Kashagan
-
Astana is expecting preliminary results on judicial claims by December, reported Reuters, citing the head of the country's Ministry of Energy, Almasadam Satkaliyev. Last year, Kazakhstan initiated arb...
-
Repairs at the “Kashagan” oil and gas field will begin on October 3, 2024, the press service of Kazakhstan's Ministry of Energy. "The Ministry confirms that the repairs at the Kashagan field will be c...
-
Partners in the North Caspian Project, QazaqGaz, the Ministry of Energy, and PSA LLP have reached an agreement on the terms for the sale of Kashagan liquefied petroleum gas (LPG) for supply to the dom...
-
Kazakhstan's arbitration claims against a group of international oil companies that developed the “Kashagan” field exceeded $160 billion after the country claimed that some transactions were involved...
-
The Japanese Inpex North Caspian Sea, which is a co-shareholder of NCOC (Kashagan), delivered the first batch of oil to Germany via the “Druzhba” pipeline in April 2024.
-
Kazakhstan has increased to $ 150 billion the amount of compensation claims against foreign oil companies developing the Kashagan oil field, Bloomberg reported.
-
The operator of the Kashagan field North Caspian Operating Company (NCOC) has paid a fine of 12.419 billion tenge ($27.7 million at the current exchange rate) for environmental violations, the press s...
-
In March 2023, the Department of Ecology of the Atyrau region identified ten violations of environmental legislation within the framework of the Kashagan project. The operator of the North Caspian...