Baku/27.11.19/ Turan: The construction of the Greek section of the Trans-Adriatic Gas Pipeline (TAP) was completed, and on November 25, the TAP consortium began to fill the 2-km gas pipeline in Greece with gas.“This is the initial stage of the pipeline commissioning process, the purpose of which is to ensure complete safety and infrastructure readiness for work after the completion of the process, in accordance with national and international saf...