Saudi company ACWA Power plans to fully commission the 240 MW Khizi-Absheron wind power plant in Azerbaijan by December 2025, the company’s manager for Azerbaijan and Türkiye, Selim Guven. "The construction of the wind power plant is progressing successfully. The plant will gradually reach its full design capacity in 2025. Specifically, the plant’s capacity will reach 80 MW in September, 160 MW in October, and 240 MW in Nove...