The newly-built Khankendi re-floated at Baku Shipyard
The Shah Deniz consortium is pleased to announce that the subsea construction vessel (SCV) “Khankendi” was recently re-floated into the Caspian Sea at the Baku Shipyard quay. The vessel has been specifically designed and built to install the subsea structures of the giant Shah Deniz Stage 2 gas development project.
This follows the safe transportation of the vessel’s hull strips from Singapore to Azerbaijan and their successful integration with bow blocks built at the Baku Shipyard on the Caspian. The Khankendi is currently 80% complete and is on track for full completion by April 2017 when Shah Deniz Stage 2 subsea construction activities are planned to commence. Until that time the vessel will be docked at the shipyard quay for completion of the remaining construction and commissioning activities.
Gordon Birrell, BP’s Regional President for Azerbaijan, Georgia and Turkey, says: “The launch of the vessel out of the dry dock at the Baku Shipyard is an important milestone achieved by Shah Deniz Stage 2 project. The Shah Deniz consortium is proud to be involved in the construction of the Khankendi, which, we believe, marks a new era in the shipbuilding history of not only Azerbaijan but also the entire Caspian region. This flagship of the Caspian oil and gas fleet is designed to construct world-class subsea structures for the first time in the Caspian at the water depth of up to 550 metres. We look forward to the full completion and commissioning of the vessel when it will be deployed to the Shah Deniz area to commence subsea installation works for the Stage 2 gas development project”.
The Khankendi is planned to perform subsea construction activities on the Shah Deniz field between 2017 and 2027. The $378 million facility is a unique vessel built under DNV GL’s (Norway and Germany) classification supervision. It is 155 meters in length, 32 meters in width and has a 13 meter main deck. The vessel will be equipped with dynamic positioning to allow working in 2.5 metre significant wave height (Hs), a 900 metric tonne main crane for 600m subsea operation, an 18-man two-bell diving system, two work-class remotely operated vehicles (ROVs), a strengthened moon pool, two engine rooms with 6x4.4MW + 2x3.2MW generators and has a total weight of 17,600 tonnes and a carrying capacity of 5,000 metric tonnes at 6.5 metres draft. –12D--
Economics
-
According to the State Customs Committee, in the first eleven months of this year, Azerbaijan transported 6.96 million tons of cargo by rail, worth $3.01 billion. This represents a 4% decrease in volume and a 10.1% decline in value compared to the same period in 2023.
-
The Cabinet of Ministers of Azerbaijan has approved a set of regulations to govern the approval of agreements under the country’s competition law, aimed at fostering compliance with legal frameworks and enhancing market transparency.
-
Azerbaijan's ambitious program to restore territories liberated from Armenian occupation has attracted attention due to the extensive use of single-source procurement methods, raising concerns about transparency and corruption.
-
Azerbaijan recorded a 2% increase in wheat imports from January to November 2024 compared to the same period in 2023, underscoring its continued reliance on external sources to meet domestic demand. This growth comes amid a significant decline in domestic wheat production, which decreased by 148,100 tons in 2024, further intensifying the need for imported supplies.
Leave a review